Obtain Utility Company Initial Approval

Submit Initial Application to the Local Utility Company

After the final design is completed, we submit a Level I application to your local utility company as required by the PA Public Utility Commission rules. We work to ensure your project is a success from start to finish. Our expertise in successfully navigating the complex permitting process sets us apart from our peers.

Receive Initial Application Approval from the Local Utility Company

When the initial application meets the utility company’s approval requirements, an “Approval to Install” notification is issued to us giving the okay to proceed with the next steps in the process. This initial notification from the utility company serves to:

  • Confirm that the utility co. has received our application.
  • Confirm that the utility co. has not found any deficiencies with the application.
  • Notification that the application has been preliminarily approved for interconnection to the grid.

This “Approval to Install” is a preliminary approval is to ensure the utility company has no issues with the final design and allows us to proceed with the next steps.